Krushi Registered Non-Profit Reg No: 3304/1997
 
  Projects
Decentralized Cotton / Yarn Unit Siricilla

Dastkaar DCY Project coordinator Ms. Vimala visited Sircilla and had a review
meeting at DCY, Sircilla on 3rd Apr 2008. The following were the discussion points.

  • It may take a period of 1-2 months for the completion of erection and trial run Hence, the official handovering of DCY-Machinery may be expected tentatively In the I week of Jun-08.
  • Due to logistic gaps, it was suggested to identify an individual house for the
    Accommodation of Dastkaar and Vortex staff. All these expenses shall be borne by Dastkaar.
  • To appoint a manager exclusively for DCY at the earliest possible and After appointment desired that Managerial training has to be given to the Manager
  • Assessed the performance of DCY Technical prepare..
  • D. Srinivas, technical instructor to prepare a work plan in Coordination with Krushi staff on weekly basis and review it on every Saturday

 

 


 